SIG Roofing

Charnley Fold, Preston 

AG was appointed by SIG Roofing to act as Project Manager, Contract Administrator, Quantity Surveyor and Principal Designer (CDM and BSA) in respect of the refurbishment project at Charnley Fold Industrial Estate, Preston.

CLIENT
SIG Roofing

LOCATION
Preston, UK 

MARKET SECTOR
Industrial/Retail 

AG ROLES
+ Project Management
+ Contract Administrator/QS
+ Principal Designer (CDM & BSA) 

PROJECT VALUE
£500k 

PROJECT DURATION
16 weeks

The proposed scheme involves:

  • Replacement of the existing asbestos roof with a composite roof covering.

  • Internal remodelling and refurbishment to create a new trade counter, staff offices and welfare areas.

Feedback from SIG Roofing:

“The branch looked great… a credit to you all. Thanks very much for all your assistance here.” – Mark Stacey

“We have opened on time as per our plan – thanks to you all for your efforts in helping us achieve this.” – Darren Beaty 

Challenge

  • To meet the client deadline to vacate from their existing site and move into the new, larger facility. 

Action

  • Arranging regular progress meetings to discuss with all stakeholders key issues.

  • Regularly reviewing the Project Risk Registers to ensure risk were identified and resolve as quickly as possible.

  • Facilitating effective communication between all stakeholders to ensure task were expedited quickly to meet deadlines.

Outcome

  • Worked with the client to ensure the works were completed in time to allow for the new branch to open in time as planned.